Project Summary
Construction of new bridge over the Ram River in Rocky Mtn House, AB. Installation and supply of 5 bridge spans, Including piling,
- Piling
- Cutoff / prep / weld plates as close to ground level as possible
- Install above ground pile assemblies / caps
- Install bridge sections
- Install deck modules
- Install End-fill materials at abutments