Back To Projects

Savona Substation Expansion

Client Name
BC Transmission Corporation
Location
Savona, BC
Started
2006
Completed
2007
Cost
$300,000.00

Project Summary

Site Grading Preparation
Prepare and level the site to the required specifications, ensuring proper drainage and stability for construction activities.

Excavation Work
Perform excavation to the specified depth for foundations, ensuring accuracy according to the project design and soil conditions.

Foundation Footings
Construct foundation footings, ensuring the correct dimensions and reinforcement to support the structure as per design requirements.

Concrete Supply and Placement
Pour and finish concrete for footings, foundations, and other structural components, ensuring adherence to strength and durability standards.

Rebar Installation
Install reinforcing steel (rebar) in accordance with structural drawings to provide additional strength and support to concrete elements.